After handover: the finished building needs cover

Practical completion and handover is the project's celebration – and the most important cut-off date in the insurance calendar: on this day, the works step out of the CAR world and into the world of operational property. There must be no gap between the two worlds, because risk never takes a break: a brand-new building can burn or flood just as easily as a half-finished one.

In brief:
  • Handover typically closes the CAR cover – the risks change genre, they don't disappear.
  • The finished works need property insurance: building, machinery, stock – with a business interruption element for an operating company.
  • The maintenance extension on the CAR side bridges the maintenance period.
  • Timing the switch: the new cover should run from the day of handover – not on a "we'll sort it out later" basis.

What closes – and what doesn't?

The cover for the construction period closes: the works are no longer contract works but a finished asset. What doesn't close, though, is the contractor's obligations during the maintenance period – that's what the maintenance extension is for – and the risks of operation don't disappear either: fire, storm, water from pipes, break-in, glass breakage, machinery breakdown. The same perils, in a different contractual framework.

The new framework: the world of property insurance

Cover for the finished premises is built differently: buildings and contents insurance, stock, electronic equipment, business interruption cover for an operating company (if production stops, the costs carry on) – and alongside it, operational liability. This is already the territory of the sister site vagyon.biz: the connecting article continues there where this one ends. As a principal, the question worth asking a month before handover is: "do we already have a quote for the operational cover?"

The choreography of the switch

The right sequence: quotes for property insurance before handover (using the finished works' data: floor area, structure, technology, values); the period of cover starting on the day of handover; activating the maintenance extension on the CAR side and notifying the fact of handover; for partial handovers, tracking section by section. The steps in a checkable form: the handover checklist. Documenting the cut-off date in writing (a handover record) is decisive for claims on both sides: the start-and-end article.

Whose job is it?

Operational insurance is the owner-operator's remit – but it's part of a good contractor's service to flag the need for the switch in good time and hand over the data for it (as-built documentation, the value of what's been built in). As a broker, I help coordinate closing the project cover and building up the operational cover, so that under the applicable terms the chance of a gap is kept as small as possible. The first step here too is a consultation: book a time.

A question tailored to your own project? Book a free 20-minute project consultation →

This article is for general information only and does not constitute an offer, or insurance or legal advice. The specific covers are determined by the insurers' terms and conditions in force at any given time; the section structure and the range of extensions vary by insurer.
Sister site in the family: vagyon.biz – property insurance for completed premises and operating businesses.