The works' value and the sum insured: what counts?

The most important figure on a CAR policy isn't the premium, but the sum insured: this is what tells you up to what value the insurer will stand behind you. If this figure sits below reality, even the finest cover is left incomplete – under-insurance isn't a theoretical risk, it's a very tangible deduction at claim-settlement time.

In brief:
  • The sum insured is the works' full reinstatement value: materials + labour + related costs.
  • Your own labour and materials received free of charge are also value – just because they weren't invoiced doesn't mean they don't need replacing.
  • In the case of under-insurance, the insurer typically settles proportionally.
  • If the project value rises along the way, the cover needs raising too – this is a routine notification.

What makes up the value of the works?

The starting point is the value under the works contract – but it doesn't always end there. It includes the cost of materials and labour, materials to be built in that are stored on site, any client-supplied materials (which the contractor doesn't invoice but which end up in the works all the same), and typically related costs: design, transport, customs, testing and commissioning. The exact scope is fixed in the wording – that's why it's worth going through the full project data sheet, question by question, when requesting a quote.

The trap of under-insurance

If works worth 100 units are insured for 60, the insurer typically settles the loss in that same proportion – even for a partial loss. This is the principle of proportional (average) settlement, and it isn't a penalty, it's the balance between premium and risk: pay a premium for half the value, and you get half the cover. The lesson is simple: setting the sum insured is not the place to optimise the premium. This genre has a relative in home insurance's under-insurance rule – the principle is the same, only the stakes are project-sized.

When the value rises along the way

Rising material costs, extra work, growing technical scope: the value of a construction project rarely stays where it was at the start. CAR can keep up with this – but only if someone tells it to. Notifying a rise in value should be as much of a routine as notifying a change of deadline: the process is shown in the change-notification article, and its contractual/tender angle in the modification article.

Practical routine at inception

Three questions are worth asking. One: does the contract value include everything that would need replacing in a claim? Two: is there client-supplied material or your own labour that doesn't show up in the invoices? Three: what's the realistic range of value movement, and how does the wording handle it (automatic tolerance, notification duty)? Anyone who can answer these three questions turns the sum insured from a risk into a strong point – the rest is added by the contract-works cover article.

A question tailored to your own project? Book a free 20-minute project consultation →

This article is for general information only and does not constitute an offer, or insurance or legal advice. The specific covers are determined by the insurers' terms and conditions in force at any given time; the section structure and the range of extensions vary by insurer.